Milton Main Street
About the project
A mammoth project to upgrade aged infrastructure underneath Milton’s main street is has been underway since June 2023.
Clutha District Council is investing $6 million to replace old water, stormwater and wastewater pipes on Union Street, between High Street to Abercrombie Street, as well as undergrounding overhead powerlines.
This project will replace critical infrastructure that has come to the end of its life and give the opportunity to upgrade pipe capacity, addressing long-standing flooding issues and planning for future growth in Milton.
Phase one of the work had progressed ahead of the contractor’s initial timeline and the stormwater and wastewater pipes have been replaced.
Phase two
Phase two of the Milton main street is to underground the overhead powerlines and the installation of a new water main along Union Street, from High Street to Abercrombie Street.
In conjunction with upgrading the water supply, underground power cabling will be installed in the footpath on both sides of Union Street within the project area.
Traffic will be able to travel in both directions but there will be safety measures and a 30km speed restriction in place.
The work is being undertaken by local contractor, Andrew Haulage (2011) while undergrounding of powerlines will be completed by PowerNet.
Underground power lines will improve the visual amenity of the main street and ensure safe, efficient and reliable power is delivered to the Milton community.
The work involves directional drilling to avoid any major road closures. There will be approximately six locations along Union Street from Arthur Street to outside Caltex where directional drilling will take place.
Once the drilling has been completed, the contractors will move into installing the underground services, both power and water on the footpath area.
The contractor will work to ensure there is access to allow people to enter shops and houses. Where there are interruptions to the footpath access and the parking lanes, one side of the path and road will be clear.
PowerNet would oversee the power cable relocation work to connect properties to the underground power supply. Then, all existing power poles and overhead lines will be removed, and new street lighting will be installed.
Once the underground cables are installed, there will be a short, planned power outage to enable the new cables to be connected to the electricity network. Affected customers will be notified of the outage by PowerNet and their electricity retailers prior to this outage.
The work site will be surrounded by safety fencing to protect people, the worksite and traffic. Traffic controllers are on site during the day to assist as well.
Improving Milton’s main street was one of the top priorities identified in the Our Place Milton community plan and the Council’s long-term plan. The main street is a busy route for motorists on State Highway 1, as well as a major focal point for the community, with many important buildings, shops, and public spaces. This project will replace critical infrastructure and is a big step towards revitalising Union Street, making it a more attractive destination.
The Milton Streetscape landscaping is a separate project and along with a new footpath, will be completed in the future.
What is happening to the main street of Milton?
We are replacing aged infrastructure with a new stormwater system along Union Street and wastewater pipes. This also gave us the opportunity to upgrade pipe capacity, addressing long-standing flooding issues and planning for future growth in Milton.
Once this is done our contractors will then work with PowerNet to install underground power cables and remove the power poles and overhead power lines. Some drinking water pipes will also be replaced while the undergrounding work is happening under the footpath.
Where is this happening?
Union Street, Milton from High Street to Abercrombie Street. Work will be completed in 50 metre sections to minimise disruption to residents, retailers and motorists as much as possible.
Why is this happening?
We are replacing aged infrastructure with a new stormwater system along Union Street and wastewater pipes. This also gave us the opportunity to upgrade pipe capacity, addressing long-standing flooding issues and planning for future growth in Milton.
We asked the community what they wanted and improving Milton’s main street was one of the top priorities identified in the Our Place Milton community plan.
Milton’s main street is a busy route for motorists on State Highway 1, as well as a major focal point for the community, with many important buildings, shops and public spaces. This project will replace critical infrastructure and is a big step towards revitalising Union Street, making it a more attractive destination.
Investing in infrastructure and promoting growth are key outcomes detailed in Council’s Living and Working in Clutha Strategy that overarch and support this project.
When is this happening?
Work started at the bottom end of High Street at the pump station on 19 June 2023, reaching Union Street intersection in approximately eight weeks. Then proceeding north section by section along Union Street, (RSA side).
Main street construction began on 3 July 2023 as contractors work along Ossian Street towards the main street and then across the main street renewing the existing wastewater pipe.
Phase two began on 6 May 2024 to underground the overhead powerlines and the installation of a new water main along Union Street, from High Street to Abercrombie Street.
How long will it take?
The entire project is expected to take over a year and there will be long term minor disruption.
Who is doing the work?
Andrew Haulage (2011) Ltd are contracted to install a new stormwater system and replace aged wastewater and drinking water pipes. PowerNet will install underground power cables and remove overhead power lines and poles.
This work is also in collaboration with Waka Kotahi as Milton's main street is also a State Highway.
How is this happening?
Contractors will work from the South end up, starting with renewal of aged utilities and installation of a new stormwater system. It will be completed in stages.
The first crew will start in South end of High Street at the Pope Street intersection on 20 June. It is expected to take this crew 8 weeks to reach the Union Street intersection (approximately 18 August 2023).
Work will start on the main street in the first week of July 2023, with replacement of wastewater pipes between Ossian and Edward streets on Union Street. Then on to Edward Street at the Ajax Street end and will take a week to get to Union Street.
Then back at the South end contractors will go along the West side of Union Street (Presbyterian Church side) and is expected to reach Abercrombie Street by 24 April 2024.
Once the stormwater and wastewater pipe work has been done on the West side contractors will move to the East side (Subway side) to begin footpath excavation for the undergrounding of powerlines and to replace some drinking water pipes. They will move along section by section to minimise disruption.
The work involves directional drilling to avoid any major road closures. There will be approximately six locations along Union Street from Arthur Street to outside Caltex where directional drilling will take place.
Once the drilling has been completed, the contractors will move into installing the underground services, both power and water on the footpath area.
PowerNet would oversee the power cable relocation work to connect properties to the underground power supply. Then, all existing power poles and overhead lines will be removed, and new street lighting will be installed.
Once the underground cables are installed, there will be a short, planned power outage to enable the new cables to be connected to the electricity network. Affected customers will be notified of the outage by PowerNet and their electricity retailers prior to this outage.
The footpath will be reinstated temporarily, as once they have completed stormwater renewals along the main street, they will then come back along pulling overhead lines and poles.
Will there be a detour?
Detours may be needed on our local roads at some stages of this work.
Is anything being done to keep traffic slowed/ensure safety on the residential streets?
There is a detailed traffic management plan for this project to ensure safety. Our contractor may report violations to Police.
What delays can I expect?
When contractors are operating stop/go motorists can expect delays of up to seven minutes. This can be related to the work to remove excavated material and old pipes when loaded onto the trucks and taken away.
Please add in extra travel time.
This work will take over a year to complete and there is potential for delays on our local roads including weather and potential heritage and cultural factors depending on what is found underground.
Council is working alongside contractors to ensure the work is done in a timely manner and people are informed of potential delays.
We will provide regular updates to keep people informed of the project’s progress to achieve the best outcomes in this period of change.
Why can’t all the work happen at the same time to reduce the amount of time businesses are disrupted?
This cannot happen because due to the sheer size of the project and number of utilities affected. It is a complex job at depth involving existing infrastructure. The length of stormwater pipe being installed is 1.5km, 375m wastewater, and 1.55km of watermain renewal. The disruption would also not be acceptable for motorists, visitors, Milton residents and businesses.
Can I still park on the main street?
Yes, just not along the section where the contractors are working.
What can my business expect in terms of parking disruption?
Parking will be affected three times. First when the stormwater installation is happening outside a business, in the parking lane then when undergrounding of power cables is being done and finally during the removal of overhead power lines and poles.
Car parks will be not be available for the section being working on, this will affect approximately 50 metres at a time.
On average parking will be out of action in front of each shop for approximately a week. Please note weather conditions may create delays to this timeframe.
Will customers be able to access shops while this work is happening?
There will still be footpath access to shops on both sides.
Each section being worked on will be surrounded by safety fencing to protect the worksite, traffic, and people.
The contractor will work to ensure there is access to allow people to enter shops and houses. Where there are interruptions to the footpath access and the parking lanes, one side of the path and road will be clear.
Is council doing anything to support affected businesses?
Council is working alongside contractors to ensure the work is done in a timely manner and businesses are informed of potential delays.
We will provide regular updates to keep businesses informed of the project’s progress.
What if I have an issue with the work outside my business?
If you have any concerns, please call Council on 0800 801 350 and staff will work to resolve the issue.
Will businesses have water during this work?
Most of the time, yes. But when a water connection needs to be commissioned, affected businesses will be contacted by the contractor in advance to arrange a suitable time.
Will this upgrade improve the risk of flooding in Milton?
We are installing a significantly bigger pipe to provide better capacity in case of heavy rain events. This will capture stormwater currently discharging from commercial and residential properties onto the street, producing overland flow down Union Street. The new system will take this stormwater into the new underground stormwater system.
Council engaged Fluent Consultants to conduct a storm disposal model. Based on their findings and subsequent designs we believe it is prudent to carry out the upgrade in conjunction with the Milton Streetscape project to improve future flooding risks.
Why are the power cables going underground?
Burying the power cables has been described as ‘instant beautification’ for the main street, as well as improving visibility for pedestrians and motorists. New streetlights will also be installed.
Will there be power outages during the work on power lines and cables?
There may be some minor power outages to allow for reconnections. This is planned for weekends to minimise disruption to retailers and business owners. PowerNet will inform affected residents of these outages.
Please contact Council on 0800 801 350 if you are experiencing any issues regarding this work and Council staff will follow up with contractors to achieve a way forward.
When was the Milton main street work decided?
In the 2018-28 Long Term Plan Council confirmed the Milton main street upgrade project as a multi-year project and set aside budget to proceed.
In May Council awarded the tender to replace aged infrastructure and the installation of a new stormwater system along Union Street (from High Street to Abercrombie Street) to Andrew Haulage for $6,295,856.86.
Is the Milton Streetscape landscaping works happening as well?
The Milton Streetscape landscaping is a separate project and along with a new footpath, will be completed in the future.
When are the contractors working?
Andrew Haulage are working Monday to Friday from 8am - 4.30pm and every second Saturday. When they are not working onsite both lanes on the main street will be open.
There may be some work done on a Sunday, particularly if they are going across the main street. By doing this work on a Sunday it is hoped to be less disruptive to motorists than during the week.